back to portal home

Phase 1: Lots 101-126

When will my land be ready? (Lots 101-126)

Civil construction

Complete

Statement of Compliance

Complete

Title Registration

Complete

Settlement

Complete

Comments

Construction Progress Video August 2024 

UPDATE  -  16  August  2024

Welcome to the Olio Phase 1 Update for August 2024!

Good progress continues to be made on the final townhomes being constructed in Phase 1, which is highlighted in the latest video.  

Our team are continuing to work with Cardinia Shire Council and Sienna Homes to maintain areas in and around Phase 1, which includes repairing cracked concrete and clearing waste and materials as appropriate.

We are pleased to advise that works will soon be commencing for the delivery of streetscape landscaping works, which will involve installation of garden beds, top soiling and grassing of naturestrips and public infrastructure areas in accordance with Council requirements.

For further information or updates on the progress of your home, please contact your nominated Building Coordinator at Sienna Homes.

For further information on the progress of maintenance and upcoming streetscape works in Phase 1, please send an email to the Olio team at olio@development.vic.gov.au.

Construction Progress Video May 2023  Click to view. To watch in larger screen mode, click on play button then click 'Youtube' heading at bottom of thumbnail.

Civil Construction Progress

construction commences
100% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction to commence once settlement on the land is achieved.

Title Registration Progress

100%
complete

settlement
100% - Complete

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75% - Complete

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - Complete

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.