Phase 2: Lots 201-338

When will my land be ready? (Lots 201-338)

Civil construction

In progress

Estimated civil construction completion timeframe

March - April 2025

Estimated Statement of Compliance timeframe

May - June 2025

Estimated title registration timeframe

May - June 2025

Estimated land settlement timeframe

June - August 2025

Estimated Townhome construction commencement timeframe

August - October 2025

Key documents

Comments

UPDATE  - 20  DECEMBER  2024

Welcome to the Olio Phase 2 Update for December 2024!  Below you’ll find information about progress of civil construction works and estimated delivery timeframes for your land.

Good progress continues to be made by Sandridge Roads on the delivery of infrastructure for Olio Phase 2, which is highlighted in the latest construction update video below.

Olio Construction Update Video - December 2024

Works to enable electrical and NBN service connections are complete with footpath and roads works in progress.

Below are the current estimated timeframes for delivery of your land, including settlement and construction commencement of your home.


Estimated Civil Construction Completion Timeframe – March - April 2025

Estimated Statement of Compliance Timeframe -    May - June 2025

Estimated Land Title Registration Timeframe – May - June 2025

Estimated Land Settlement Timeframe – June - August 2025

Estimated Townhouse Construction Commencement Timeframe – August - October 2025

For further enquiries about the progress of civil construction works in Phase 2, please send an email to the Olio team at olio@development.vic.gov.au.

Construction Progress Video August 2024

Civil Construction Progress

construction commences
80% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
In Progress
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction to commence once settlement on the land is achieved.