Release 10 - Lots 107 to 117

When will my home be ready? (Lots 107-117)

Estimated Civil construction completion

March - April 2027

Estimated Land Title Registration

March - April 2027

Estimated Land Settlement

March - May 2027

Estimated Home Construction Commencement timeframe

Jun -Aug 2027

Civil Construction Progress

construction commences
% COMPLETE
construction complete
Pre-Construction
In Progress
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
water
Provision of water connection to each lot. Estimated timeframe 3-4 weeks.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction to commence once settlement on the land is achieved.

Title Registration Progress

0%
complete

settlement
100%

Contact made by Development Victoria to purchaser's legal representatives / conveyancers to initiate settlement process (settlement can occur at any time up to 14 days after title registration is achieved). Soil testing by builders and bank valuations can be undertaken at this point.

Title registration
75%

Document lodged to Land Titles Victoria to enable title registration. Estimated timeframe for title registration following lodgement 10-14 days.

statement of
compliance
50% - In Progress

Document received from local council confirming construction has been completed in accordance with approved plans developed by the relevant authorities.

Home Construction Progress

home construction commences
0% COMPLETE
home construction complete
slab
In Progress
Concrete footings for base is poured.
frame
Construction and set-up of frame for approval by a building surveyor.
lock up
External wall cladding and roof covering is completed, flooring is laid and external doors and external windows are fixed.
internal
fit out
All internal fittings including architraves, skirting, doors, built-in shelves, baths, basins, troughs, sinks, cabinets and cupboards are fitted or fixed into position.
landscaping
Planting of street trees for nature strips and trees in common areas as appropriate and landscaping in and around properties.
practical
completion
All building work is either complete or close to completion, in accordance with the contract/agreement with the relevant authorities. Property is reasonably fit for occupation.
Settlement and Handover
Refer to the ‘Settlement and Handover’ timeline below and attached in ‘Key Documents’.
Post Handover
Refer to the Handover Guide for more information.