Phase 2: Lots 201-338

When will my land be ready? (Lots 201-338)

Civil construction

In progress

Estimated civil construction completion timeframe

March - April 2025

Estimated Statement of Compliance timeframe

May - June 2025

Estimated title registration timeframe

May - June 2025

Estimated land settlement timeframe

May - June 2025

Estimated Townhome construction commencement timeframe

July - August 2025

Key documents

Civil Construction Progress

construction commences
25% COMPLETE
construction complete
Pre-Construction
Includes design, authority approvals, tender and audit works.
Earthworks
Re-shaping of the ground to allow construction of roads and drainage connection to each lot. Estimated timeframe 4-6 weeks.
sewer and
drainage
In Progress
Provision of a sewer connection to each lot and underground drainage system. Estimated timeframe 8 weeks.
water and gas
Provision of water and gas pipeline connections to each lot. Estimated timeframe 3-4 weeks.
sub-grade
Developing a firm material base underneath roads and footpaths. Construction of kerbs and drains to enable channels from stormwater to travel to underground drainage system.
electrical and nbn
Electrical cabling and NBN to enable internet connection for each lot.
Footpaths
and roads
Footpaths, asphalt, topsoiling and road completion.
construction
complete
Completion of the construction works. Home construction to commence once settlement on the land is achieved.